Document control record
A person using Aurecon documents or data accepts the risk of:
a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.
b) Using the documents or data for any purpose not agreed to in writing by Aurecon.
Author signature |
|
Certified by |
|
Name |
Oliver Chiu |
Name |
F. C. Tsang |
Title |
Environmental Team Consultant |
Title |
Environmental Team Leader |
Contents
1.2 Construction Works Programme
1.4 Construction Works Programme and Construction Works Area
1.5 Works undertaken during the Period
2.3 Monitoring Parameter and Frequency
2.4 Action and Limit Level for Water Quality Monitoring
2.6 Results and Observations. 8
2.7 Quarterly Assessment of Construction Impacts on Suspended Solids at the Project Site
3.2 Noise Monitoring Parameter, Frequency and Duration
3.3 Action and Limit Levels. 12
3.4 Results and Observations. 12
7.2 Results and Observations. 17
9 Environmental Site Inspection and Audit
9.1 Implementation Status of Environmental Mitigation Measures
10 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
10.2 Summary of Environmental Non-Compliance
10.3 Summary of Environmental Complaint
10.4 Summary of Environmental Summon and Successful Prosecution
11 Conclusions and Recommendations
11.2
Comments/ Recommendations
Appendices
Appendix
1.1 Construction Programme
Appendix
1.2 Project Organization Chart
Appendix
2.1 Event and Action Plans for Water Quality
Appendix
2.2 Graphical Presentation of Water Quality Monitoring
Appendix
3.1 Event and Action Plans for Noise
Appendix
3.2 Graphical Presentation of Noise Monitoring
Figures
Figure 1.2.. Location of
Work Areas for the Project
Figure 2.1.. Impact
Water Quality Monitoring Locations
Figure 3.1.. Impact
Noise Monitoring Locations
Figure 8.1.. Area for
Archaeological Survey
Figure 8.3.. Monitoring
Locations of Lan Fong Study Hall at Ha Che
Figure 8.4.. Monitoring
Locations of St. John’s Chapel near Tai Wo
A1. Drainage Services Department (DSD) has appointed Aurecon Hong Kong Limited (Aurecon) to undertake the Environmental Team services for the project and implement the EM&A works.
A2. The construction works commenced on 20 February 2024.
A3. This 5th Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. DC/2022/02 Drainage Improvement Works at Yuen Long – Stage 2 (hereinafter called the “Contract”). The report summaries the findings of the EM&A programme during the reporting period from 1 February 2025 to 30 April 2025.
A4. A summary of construction activities undertaken during the reporting period is presented below:
Ha Che
§ Site clearance;
§ Breaking ground;
§ Temporary drainage diversion;
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting;
§ Sheet pilling & backfilling and compaction; and
§ Removal of sheet piles, drain laying works, reinstatement.
Lin Fa Tei
§ Site clearance;
§ Temporary drainage diversion;
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting; and
§ Sheet pilling & backfilling and compaction;
§ Removal of sheet piles, drain laying works, reinstatement.
Sung Shan New Village
§ Site clearance;
§ Temporary drainage diversion;
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting;
§ Sheet pilling & backfilling and compaction; and
§ Removal of sheet piles, drain laying works, reinstatement.
Tai Wo
§ No construction activities (from 1 April 2025 to 30 April 2025)
§ Site Clearance
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
Water Quality
A5. The summary of exceedance records during the reporting period is summarized in Table A1.
Table A1 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen (DO) |
1 |
0 |
1 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
Suspended Solids (SS) |
0 |
0 |
0 |
0 |
0 |
0 |
A6. One (1) action level exceedance for DO were recorded during the reporting period. After investigation of above the exceedances, it was considered to non-project related.
Noise
A7. No Action Level or Limit Level exceedance was recorded for construction noise monitoring during the reporting period.
Built Heritage
A8. No monitoring exceedance was recorded in the reporting period.
A9. Two environmental complaints were received during the reporting period. The investigation results for the environmental complaint regarding air quality and environmental complaint regarding waste management on 19 February 2025 had been investigated during the reporting period. The summary of the investigation results was presented below:
Environmental Complaint regarding air quality on 19 February 2025
A10. It was recorded that a complaint regarding air quality was received by the EPD on 17 February 2025 and referred to DSD, ET and IEC on 19 February 2025. The complaint was related to the lack of dust suppression measures from the construction site at Tai Wo.
A11. Under the investigation, the precautionary dust suppression measures were implemented on site before and on 17 February 2025 by the contractor. The following measures included:
§ Regular watering had been provided for excavated works sites and main haul road;
§ Water spraying for vehicle wheeling washing and dust suppression at the exit of the construction sites;
§ Paving haul road with concrete to reduce generation of fugitive dust during vehicle travelling; and
§ Covering open stockpiles.
A12. To enhance the dust suppression on site, the Contractor had implemented the following measures after 17 February 2025:
§ Increasing watering frequency on excavated work sites and main haul roads;
§ Ensuring all excavated work sites and main haul roads had adopted proper and regular watering;
§ Ensuring water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
§ Avoiding open stockpiles placing near air sensitive receivers and ensuring that the stockpiles are covered with tarpaulin when they are not in use.
A13. During the site investigation conducted by the ET at Tai Wo on 21 February 2025, the ET observed that:
§ No muddy material on the main access road adjacent to the construction site;
§ Water spraying has been adopted on main haul road and exposed area;
§ Water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites. Cleaning has been deployed to prevent muddy stain left
§ behind on public access road;
§ Stockpiles are covered with tarpaulin; and
§ No observation of fugitive dust.
A14. Based on the information provided by the Contractor and information collected from the site inspection, it concluded that dust suppression measures have been properly implemented on site to mitigate dust impact on the nearby residents. No deficiency observation in relation to fugitive dust impact were recorded during the site inspections on 21 February 2025. After the complaint, the Contractor has enhanced and properly implemented the precautionary and mitigation measures to suppress dust from the work area and within the site boundary. As no further complaint of lacking dust suppression measures was received, the case is considered closed.
Environmental Complaint regarding waste management on 19 February 2025
A15. It was recorded that a complaint regarding waste management was received by the EPD on 16 February 2025 and referred to the DSD, the ET and the IEC on 19 February 2025. The complaint was related to the fly-tipping of construction waste from the construction site at Tai Wo.
A16. A site investigation was conducted by the ET at Tai Wo on 21 February 2025. During the site investigation, the ET observed that:
§ No construction waste was found within the work area at Tai Wo;
§ Stockpile of materials within the site working area was properly covered with tarpaulin;
§ A construction working area that is not related to the Project was observed near the vehicle washing facility. Construction materials that are not related to the Project were found near the vehicle washing facility but were lying outside the working area.
A17. No environmental deficiency was observed during the site investigation on 21 February 2025.
A18. Based on the information provided by the Contractor and the information collected from the site inspection, no construction waste was observed at the work area in Tai Wo. Construction materials that were considered as project non-related, was observed on the public access road at Cheung Po Tsuen. Therefore, it is concluded that the complaint is invalid.
A19. No notification of summons or successful prosecutions was received in the reporting period.
A20. Construction works at Tai Wo are only allowed during dry season (i.e.
October to March) in accordance with Condition 3.2 of EP No. EP-596/2021.
Impact noise monitoring, impact water quality monitoring and weekly site
inspection at Tai Wo were resumed starting from 1 February 2025 during the last
dry season (i.e. October 2024 to March 2025). The construction work at Tai Wo
was temporarily suspended since 1 April 2025 in
accordance with the requirement stipulated in Condition 3.2 of EP No.
EP-596/2021, thus, no impact noise monitoring, impact water quality monitoring
and weekly site inspection was carried out during the above period.
Diagram 1.1 Organisation Chart
Table 1.1 Parties Involved in Project Organisation
Parties |
Organization / Company |
Project Proponent |
Drainage Services Department |
Supervisor / Engineer’s Representative (ER) |
Atkins China Ltd |
Contractor |
Wing Tat Civil Engineering Co. Limited |
Environmental Team (ET) |
Aurecon Hong Kong Limited |
Independent Environmental Checker (IEC) |
Mott MacDonald Hong Kong Limited |
§ Site clearance; work
§ Breaking ground
§ Temporary drainage diversion
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting
§ Sheet pilling & backfilling and compaction; and
§ Removal of sheet piles, drain laying works, reinstatement.
Lin Fa Tei
§ Site clearance work
§ Temporary drainage diversion
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting; and
§ Sheet pilling & backfilling and compaction
§ Removal of sheet piles, drain laying works, reinstatement.
Sung Shan New Village
§ Site clearance work
§ Temporary drainage diversion
§ Excavation and Lateral Support, relocate/ divert utilities, rebar fixing, formwork erection and cast-in, concreting
§ Sheet pilling & backfilling and compaction; and
§ Removal of sheet piles, drain laying works, reinstatement.
Tai Wo
§ No construction activities (from 1 April 2025 to 30 April 2025)
§ Site Clearance work
§ Temporary Drainage Diversion
§ Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting
Table 2.1 Summary of Impact Water Quality Monitoring Stations
Stream |
Monitoring ID |
Coordinates (HK Grid) |
Remarks |
|
Easting |
Northing |
|||
SSNV |
C1A (1) |
821702 |
831945 |
Alternative Impact Monitoring Point |
C2 |
822459 |
831470 |
Control Monitoring Point |
|
C3A (2) |
822413 |
831284 |
Alternative Control Monitoring Point |
|
TW |
C4 (4) |
825497 |
830664 |
Control Monitoring Point |
C5 (4) |
825486 |
830716 |
Impact Monitoring Point |
|
LFT |
C6 |
827232 |
831713 |
Control Monitoring Point |
C7A (3) |
826865 |
832115 |
Alternative Control Monitoring Point |
|
C8 |
826513 |
832075 |
Impact Monitoring Point |
|
HC |
C9 |
828304 |
835029 |
Control Monitoring Point |
C10 |
827919 |
834271 |
Impact Monitoring Point |
Notes:
(1) At Station C1, access to safe sampling of water is not feasible due to steep banks on both sides of the stream channel. An alternative monitoring location is proposed at Station C1A, which is about 250 m along the same stream channel downstream of Station C1 and is accessible for safe water sampling.
(2) During the first day of baseline monitoring at Station C3, shallow water was observed, and the ET could not sample enough water for monitoring. As agreed by the ER, the Contractor, and the IEC, a new sampling location, Station C3A, was identified at about 130 m upstream and was accessible for water sampling.
(3) For Station C7, the location is not close to the nearest, revised works boundary (about 200 m away). An alternative monitoring location is proposed at Station C7A, which is about 23 m upstream of the nearest, revised works boundary.
(4) Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No. EP-596/2021. Impact water quality monitoring at Tai Wo were resumed starting from 1 February 2025 during the last dry season (i.e. October 2024 to March 2025). The construction work at Tai Wo was temporarily suspended since 1 April 2025 in accordance with the requirement stipulated in Condition 3.2 of EP No. EP-596/2021, thus, no impact noise monitoring, impact water quality monitoring and weekly site inspection was carried out during the above period.
Table 2.2 Parameters measured in the Impact Water Quality Monitoring
Parameter |
Frequency |
Duration |
Stream |
Monitoring ID |
Dissolved oxygen (DO), temperature, turbidity, salinity, pH, stream water depth and suspended solids (SS) |
1 day in a week (1) |
Throughout the construction phase |
SSNV |
C1A |
C2 |
||||
C3A |
||||
LFT |
C6 |
|||
C7A |
||||
C8 |
||||
HC |
C9 |
|||
C10 |
||||
3 days in a week |
TW(2) |
C4 |
||
C5 |
Notes:
(1) Impact monitoring shall be carried out 3 days per week during the construction process. The monitoring frequency can be reduced to once per week, with sampling/ measurement at the designated monitoring locations when no exceedances were recorded during the past three-month period in accordance with Section 2.7, Appendix 4 of the Updated EM&A Manual. The change of the monitoring frequency at SSNV, LFT and HC was approved by EPD on 25 November 2024. Hence, the monitoring frequency at SSNV, LFT and HC was changed to 1 day in a week starting from 2 December 2024.
(2) No construction work would be undertaken at Tai Wo between April and September under Condition 3.2 of EP No.: EP-596/2021. Thus, impact water quality monitoring at C4 and C5 was suspended in April 2025.
Table 2.3 Action and Limit Levels for Water Quality
Parameters |
Action Level |
Limit Level |
DO in mg/L |
< 5%-ile of baseline data |
< 4 mg/L or < 1%-ile of baseline data |
SS in mg/L |
> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher |
> 99%-ile of baseline data or 130% of upstream control station of the same day, whichever is higher |
Turbidity in NTU |
> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher |
> 99%-ile of baseline data or > 130% of upstream control station of the same day, whichever is higher |
Note:
(1) For DO, non-compliance of the water quality limit occurs when monitoring result is lower than the limit.
(2) For SS and turbidity, non-compliance of the water quality limit occurs when monitoring result is higher than the limit.
(3) All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered necessary.
Table 2.4 Action and Limit Levels of Water Quality
Monitoring ID |
Parameters |
Action |
Limit |
|
SSNV |
C1A |
DO in mg/L |
<6.72 |
<4 (1) |
SS in mg/L |
>7.3 or >120% of upstream control station of the same day, whichever is higher |
>8.5 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>10.37 or >120% of upstream control station of the same day, whichever is higher |
>10.81 or > 130% of upstream control station of the same day, whichever is higher |
||
TW |
C5 |
DO in mg/L |
<8.36 |
<4 (2) |
SS in mg/L |
>9.9 or > 120% of upstream control station of the same day, whichever is higher |
>10.0 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>13.64 or > 120% of upstream control station of the same day, whichever is higher |
>13.87 or > 130% of upstream control station of the same day, whichever is higher |
||
LFT |
C8 |
DO in mg/L |
<5.38 |
<4 (3) |
SS in mg/L |
>6.3 or > 120% of upstream control station of the same day, whichever is higher |
>7.0 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>12.46 or > 120% of upstream control station of the same day, whichever is higher |
>12.94 or > 130% of upstream control station of the same day, whichever is higher |
||
HC |
C10 |
DO in mg/L |
<2.55 |
<2.43 (4) |
SS in mg/L |
>8.7 or > 120% of upstream control station of the same day, whichever is higher |
>8.8 or > 130% of upstream control station of the same day, whichever is higher |
||
Turbidity in NTU |
>20.06 or > 120% of upstream control station of the same day, whichever is higher |
>21.07 or > 130% of upstream control station of the same day, whichever is higher |
(1) The 1%-ile of baseline DO data at C1A is 6.61 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(2) The 1%-ile of baseline DO data at C5 is 8.09 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(3) The 1%-ile of baseline DO data at C8 is 5.36 mg/L, which is higher than 4 mg/L. Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.
(4) The 1%-ile of baseline DO data at C10 is 2.43 mg/L, which is lower than 4 mg/L. Taking account of the baseline water quality condition and to minimise any false alarm of water quality deterioration during construction phase, DO concentration of 2.43 mg/L is adopted as the limit level.
Table 2.5 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
1 |
0 |
1 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
Suspended Solids |
0 |
0 |
0 |
0 |
0 |
0 |
Action Level Exceedance for DO on 28 March 2025
Table 2.6 Comparison of the difference between the quarterly mean and 1.3 times of the ambient mean
Parameter |
Monitoring Location |
Quarterly Mean of SS (mg/L) |
Baseline Level of SS (mg/L) |
1.3 Times of Ambient Mean (mg/L) (1) |
Quarterly Mean of SS > 1.3 Times of Ambient Mean (Y/N) |
Request of Further Mitigation Measures (Y/N) |
Suspended Solids |
C1A |
3.6 |
4.8 |
6.2 |
N |
N |
C2 (Control Point) |
8.5 |
3.2 |
4.2 |
Y |
N/A |
|
C3A (Control Point) |
4.8 |
2.2 |
2.9 |
Y |
N/A |
|
C4 (Control Point) |
32.1 |
10.7 |
13.9 |
Y |
N/A |
|
C5 |
2.1 |
5.2 |
6.8 |
N |
N |
|
C6 (Control Point) |
17.0 |
3.7 |
4.8 |
Y |
N/A |
|
C7A (Control Point) |
8.0 |
6.7 |
8.7 |
N |
N/A |
|
C8 |
2.3 |
4.0 |
5.2 |
N |
N |
|
C9 (Control Point) |
11.7 |
5.9 |
7.7 |
Y |
N/A |
|
C10 |
4.6 |
8.5 |
11.1 |
N |
N |
Note:
(1) 1.3 times of the ambient mean equal to be defined as 30% increase of the baseline data.
Sung Shan New Village (Monitoring Locations C1A, C2 & C3A)
Tai Wo (Monitoring Locations C4 & C5)
Lin Fa Tei (Monitoring Locations C6, C7A & C8)
Ha Che (Monitoring Locations C9 & C10)
Table 3.1 Noise Monitoring Stations during Construction Phase
ID No. (1) |
Location |
Nature of Uses |
Type of Measurement |
SSNV_M2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720 S.A) |
Residential |
Façade |
SSNV_M3 |
Village house near a soybean sauce factory in Sung Shan New Village (near DD118 1712) |
Residential |
Façade |
SSNV_M6 |
#43, Sung Shan New Village |
Residential |
Free-field |
TW_M2 (4) |
#200, Cheung Po |
Residential |
Free-field |
TW_M3 (4) |
Kai Yip Garden, #3H, Tai Wo |
Residential |
Free-field |
LFT_M1 |
#2G, Lin Fa Tei |
Residential |
Façade |
LFT_M3A (2) |
Near #125B, Lin Fa Tei |
Residential |
Free-field |
LFT_M5 |
#156B, Lin Fa Tei |
Residential |
Façade |
LFT_M6 (3) |
Village house near the nullah (DD112 699 S.E) |
Residential |
Façade |
LFT_M11 (2) |
#210, Ngau Keng Tsuen |
Residential |
Façade |
HC_M3A (2) |
Next to DD111 326 S.B RP near Fan Kam Road |
- |
Free-field |
HC_M4 |
#1C, Chuk Hang |
Residential |
Façade |
HC_M6 |
The Arbutus House 12, #52, Shui Kan Shek |
Residential |
Façade |
Notes:
(1) SSNV – Sung Shan New Village; TW – Tai Wo; LFT – Lin Fa Tei; HC – Ha Che.
(2) LFT_M3A, LFT_M11, HC_M3A and are alternative noise monitoring stations proposed to replace LFT_M3, LFT_M13 and HC_M3, respectively.
(3) Due to the objection from property management office for providing access to designated monitoring location, the noise monitoring at LFT_M7 have been suspended since 27 March 2024. An alternative monitoring location LFT_M6 was proposed to replace LFT_M7 and agreed with the ER and the IEC.
(4) Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No. EP-596/2021. Impact noise monitoring at Tai Wo was resumed starting from 1 February 2025 during the last dry season (i.e. October 2024 to March 2025). The construction work at Tai Wo was temporarily suspended since 1 April 2025 in accordance with the requirement stipulated in Condition 3.2 of EP No. EP-596/2021, thus, no impact noise monitoring, impact water quality monitoring and weekly site inspection was carried out during the above period.
Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
SSNV_M2, SSNV_M3, SSNV_M6, HC_M3A, HC_M4, HC_M6, TW_M2, TW_M3, LFT_M1, LFT_M3A, LFT_M5, LFT_M6 and LFT_M11 |
Leq(30mins) (as a logarithmic average of 6 consecutive Leq(5mins)) |
Once every week throughout the construction phase between 0700 and 1900 on normal weekdays |
Table 3.3 Action and Limit Levels for Construction Noise Monitoring
Time Period |
Action |
Limit Level |
07:00 – 19:00 on normal weekdays |
When one or more documented complaints are received |
75 dB(A)(1) |
07:00 – 23:00 on holidays; and 19:00 – 23:00 on all other days |
45 dB(A)(2) |
|
23:00 – 07:00 of the next day |
30 dB(A)(2) |
Notes:
(1) Between 07:00 and 19:00, construction noise limit for school during normal term time is 70 dB(A) and 65 dB(A) during examination period.
(2) The ASR of identified noise sensitive receivers is “A”, which is a rural area that is not affected by the in Influencing Factors (Ifs). The limit levels are stipulated in the Technical Memorandum on Noise from Construction Work in Designated Areas.
Post-translocation Monitoring
Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings
Graded Historic Buildings |
Mitigation Measures |
Lee Tat Bridge, Shui Tsan Tin (Grade 3) |
§ A condition survey should be carried out in advance of works and after completion of works by qualified building surveyor or structural engineer. The Condition Survey Report should contain descriptions of the structure, identification of fragile elements, an appraisal of the condition and working methods for any proposed monitoring and precautionary measures that are or were recommended with aid of photo records. The condition survey report must be submitted to the AMO for comment before construction activities commence and after the works have been completed. The contractor should implement the approved monitoring and precautionary measures. § Vibration, settlement and tilting monitoring should be undertaken during the construction works to ensure that safe levels of vibration are not exceeded. An Alert, Alarm and Action (AAA) vibration limit set at 5 / 6 / 7.5 mm/s for Grade 3 historic buildings, settlement limit set at 6/ 8/ 10mm, and tilting limit set at 1/2000; 1/1500; 1/1000 should be adopted. Monitoring proposal, including checkpoint locations, installation details, response actions for each of the AAA levels and frequency of monitoring should be submitted for AMO's consideration. Installation of monitoring checkpoints shall be carried out in great care and adequate protection shall be provided so as to avoid unnecessary disturbance/ damage to the historic fabrics. Photo records of monitoring checkpoints shall be submitted upon installation for AMO's records. Monitoring records should be submitted to AMO on regular basis and alert AMO should the monitoring reach AAA levels. |
Lan Fong Study Hall, Chuk Hang (Grade 3) |
|
St John’s Chapel, Cheung Po (Grade 2) |
Table 9.1 Site Observations
Date |
Environmental Observations |
Follow-up Status |
5 Feb 2025 |
Observation(s) and Recommendation(s)
Ha Che: 1. The Contractor was reminded to place the updated CNP on site. |
Ha Che: 1. The updated CNP has been displayed on site by the contractor. |
12 Feb 2025 |
Observation(s) and Recommendation(s)
Lin Fa Tei: 1. The Contractor was reminded to direct waterflow to the wastewater treatment system before discharge especially during rainy day. |
Lin Fa Tei: 1. The water flow was redirected to the wastewater treatment system before discharge by the contractor. |
19 Feb 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
26 Feb 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
5 Mar 2025 |
Observation(s) and Recommendation(s)
Sung Shan New Village: 1. Waste near the geotextile should be removed regularly. |
Sung Shan New Village: 1. Waste near the geotextile have been removed by the contractor. |
12 Mar 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
19 Mar 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
26 Mar 2025 |
Observation(s) and Recommendation(s)
Ha Che: 1. Chemical should probably store. |
Ha Che: 1. Chemical has been properly stored by the contractor. |
2 April 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
9 April 2025 |
Observation(s) and Recommendation(s)
Ha Che: 1. Environmental permit should be displayed on site. |
Ha Che: 1. Environmental Permit has been displayed properly on site. |
16 April 2025 |
Observation(s) and Recommendation(s)
Nil |
Nil |
23 April 2025 |
Observation(s) and Recommendation(s)
Sung Shan New Village: 1. Impervious sheeting should be provided for placing the breaker to prevent land contamination on site. |
Sung Shan New Village: 1. The breaker has been covered by impervious sheeting to prevent land contamination on site. |
30 April 2025 |
Observation(s) and Recommendation(s)
Sung Shan New Village: 1. The Contractor should regularly maintain the condition of geotextile and remove waste nearby. |
Sung Shan New Village: 1. The Contractor has properly maintained the condition of geotextile and remove waste nearby. |
Table 10.1 Summary of Exceedance Records of Water Quality Monitoring
Parameter |
No. of non-project related exceedances |
Total No. of non-project related exceedances |
No. of exceedance related to the Project |
Total No. of exceedance related to the Project |
||
AL |
LL |
AL |
LL |
|||
Dissolved Oxygen |
1 |
0 |
1 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
Suspended Solids |
0 |
0 |
0 |
0 |
0 |
0 |
28 March 2025
Environmental Complaint regarding air quality on 19 February 2025
§ Regular watering had been provided for excavated works sites and main haul road;
§ Water spraying for vehicle wheeling washing and dust suppression at the exit of the construction sites;
§ Paving haul road with concrete to reduce generation of fugitive dust during vehicle travelling; and
§ Covering open stockpiles.
§ Increasing watering frequency on excavated work sites and main haul roads;
§ Ensuring all excavated work sites and main haul roads had adopted proper and regular watering;
§ Ensuring water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites; and
§ Avoiding open stockpiles placing near air sensitive receivers and ensuring that the stockpiles are covered with tarpaulin when they are not in use.
§ No muddy material on the main access road adjacent to the construction site;
§ Water spraying has been adopted on main haul road and exposed area;
§ Water spraying for vehicle wheel washing and dust suppression has been adopted at the exit of the construction sites. Cleaning has been deployed to prevent muddy stain left behind on public access road;
§ Stockpiles are covered with tarpaulin; and
§ No observation of fugitive dust.
Environmental Complaint regarding waste management on 19 February 2025
§ No construction waste was found within the work area at Tai Wo;
§ Stockpile of materials within the site working area was properly covered with tarpaulin;
§ A construction working area that is not related to the Project was observed near the vehicle washing facility. Construction materials that are not related to the Project were found near the vehicle washing facility but were lying outside the working area.
Noise
§ Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and
§ Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.
Water Quality
§ No effluent discharge would be allowed before acquired the effluent discharge license;
§ Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;
§ Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;
§ Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;
§ Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and
§ Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.
Waste Management
§ Provision of sufficient waste disposal points and regular collection of waste;
§ Regular cleaning and maintenance programme for drainage system; and
§ Chemical containers shall be stored with drip tray underneath.
Ecology
§ Minimize loss of habitats and associated wildlife; and
§ Using directional lighting to prevent excessive light spill into adjacent natural habitat and disturbance to nocturnal fauna.
Landscape and Visual
§ Construction activities shall be carefully designed to minimize impact on existing retained trees; and
§ Adequate tree protection measures shall be provided for the trees to be retained on site.